Applied Digital’s newest data center lease pays about $2.00 million a year for each megawatt of capacity, 18% more than the average of the company’s five earlier leases, TECHi calculates from a lease-by-lease table in the investor presentation Applied Digital filed with the Securities and Exchange Commission on Wednesday evening. The 150-megawatt lease, signed with a tier-one investment-grade hyperscaler the company has not named and announced on Monday, is worth $5.40 billion over an 18-year base term.
Applied Digital’s shares were up 6.8% at $13.13 in pre-market trading on Friday at 7:26 a.m. Eastern, according to Nasdaq data, after jumping 20.3% on Monday and falling 11.6% on Tuesday. They ended Wednesday 31% below their October 30 close and about 75% below their closing high of $49.65 on May 28. The same presentation shows how much of the contracted capacity is still being built and how the company plans to pay for it.
Article Brief
Key Takeaways
5 Points30s Read
- New lease$5.40 billion over 18 years is $300 million a year, or about $2.00 million per megawatt.
- ComparisonThat is 18% above the $1.69 million average of Applied Digital’s five earlier leases, TECHi calculates.
- Build costAt the company’s $11 million to $13 million per megawatt, the 1,285 MW under construction would cost $14.1 billion to $16.7 billion in total.
- FinancingA $300 million bridge loan for Louisiana and a larger B. Riley preferred facility, with $1.035 billion left to draw.
- SharesUp 6.8% before Friday’s open, after a 31% fall in November through Wednesday.
What does the new lease pay?
The presentation lists each of Applied Digital’s six leases with its capacity, base term and expected base-term value. Dividing that value by the term gives an average annual rent, which is the method the company itself uses in the same document to estimate operating income for each site. For the new lease, $5.40 billion over 18 years works out to $300 million a year, or about $2.00 million for each of its 150 megawatts, TECHi calculates.
The company said in its Monday announcement that the lease has improved commercial terms over its prior leases, “including higher pricing”. The table lets that claim be measured. The figures exclude pass-through power, so they cover the data center capacity rather than the electricity the tenant uses.
Delivery of the new capacity is expected to begin in the first half of 2028 and continue into the second half, and the company has not said where the campus will be. The lease is subject to conditions including approvals of a power supply agreement, according to the presentation.
| Campus | Tenant | Capacity | Base term | Base-term value | Rent per MW a year |
|---|---|---|---|---|---|
| Polaris Forge 1 (N.D.) | CoreWeave | 400 MW | 15 years | $10.71B | $1.79M |
| Polaris Forge 2 (N.D.) | Investment-grade | 200 MW | 15 years | $4.82B | $1.61M |
| Polaris Forge 3 (N.D.) | High investment-grade | 300 MW | 15 years | $7.50B | $1.67M |
| Delta Forge 1 (La.) | High investment-grade | 300 MW | 15 years | $7.50B | $1.67M |
| Delta Forge 2 (Ala.) | High investment-grade | 210 MW | 15 years | $5.20B | $1.65M |
| New lease (not disclosed) | High investment-grade | 150 MW | 18 years | $5.40B | $2.00M |
How does it compare with the earlier leases?
The new lease is the most expensive in the portfolio on this measure. The two 300-megawatt leases at Polaris Forge 3 in North Dakota and Delta Forge 1 in Louisiana, both with high investment-grade hyperscalers, average about $1.67 million per megawatt a year, so the new lease pays 20% more. It pays 21% more than the 210-megawatt Delta Forge 2 lease in Alabama and 24% more than the two Polaris Forge 2 leases at Harwood, North Dakota, the lowest on the list.
CoreWeave’s 400-megawatt lease at Ellendale, North Dakota, the only one in the portfolio with a tenant below investment grade, pays about $1.79 million per megawatt a year. That was more per megawatt than any of the investment-grade leases signed before this month, and the new lease pays 12% more again.
There is a limit to the comparison. Averages over a full term hide how the rent is set from year to year, and many data center leases rise by a fixed percentage each year. If that is the case here, an 18-year lease would show a higher average than a 15-year lease at the same starting rent, so part of the gap could come from the longer term rather than a higher price. The presentation does not give escalation terms, and TECHi cannot separate the two effects from the filing.
What would the lease earn against its cost?
Applied Digital expects a stabilized net operating income margin of 85%, plus or minus three points, at the new site, which gives about $255 million a year of net operating income once all the capacity is billing. The company estimates construction costs of $11 million to $13 million per megawatt across its campuses, which puts the new 150 megawatts at $1.65 billion to $1.95 billion.
On those figures, the new lease’s yearly operating income would equal 13.1% to 15.5% of its construction cost, TECHi calculates, against 10.9% to 12.9% for Polaris Forge 3 and Delta Forge 1 and 12.1% to 14.3% for CoreWeave’s lease. Net operating income is a non-GAAP measure that leaves out interest, depreciation and corporate costs, and the company describes all of these site figures as forward-looking and not guidance.
How much does Applied Digital still have to build?
Most of the contracted capacity is still being built. According to the presentation, 275 megawatts are operating and 1.285 gigawatts are under construction, with all of the contracted capacity due for delivery by 2028. At the company’s own cost range, the 1,285 megawatts under construction would cost $14.1 billion to $16.7 billion in total, TECHi calculates, a figure that includes money already spent on sites under way. Applied Digital had $2.95 billion of cash at the end of August, according to its latest quarterly report.
The company plans to fund most of that with partners and project debt. Under a partnership of up to $5 billion with Macquarie Asset Management, Macquarie expects to invest $2.25 million of preferred equity per megawatt leased to investment-grade tenants, carrying a 12.75% dividend that can be paid in kind rather than cash for the first five years, and receives a 15% common stake in the Applied Digital subsidiary that holds those data centers, according to the presentation, which says parts of the arrangement are subject to final documentation. Project loans of up to 80% of cost cover most of the rest. For the new lease, that would mean about $338 million from Macquarie and $1.32 billion to $1.56 billion of debt, TECHi calculates.
Chief Financial Officer Saidal Mohmand said the company expects to complete the remaining project financing for Delta Forge 1 and Polaris Forge 3 in the first quarter of 2027, followed by Delta Forge 2 in the second quarter.
What did this week’s financing filings add?
In a filing on Tuesday afternoon, Applied Digital said it had raised the size of its preferred equity purchase agreement with three B. Riley entities from $2.0 billion to $2.5 billion, leaving $1.035 billion available to draw. The agreement covers Series G convertible preferred stock, which can be converted into common shares. The amount still available equals about 28% of the company’s market value at Wednesday’s close, TECHi calculates from the 302.4 million shares outstanding on October 6, though the number of common shares it could become depends on conversion terms not set out in this filing.
The company also closed a $300 million bridge loan for Delta Forge 1. It is a 364-day delayed-draw term loan at the Secured Overnight Financing Rate plus three percentage points, and draws depend on conditions that include construction milestones and state commission approval of electrical rates. Applied Digital said it expects to seek additional financing to finish the Louisiana campus.
How have the shares traded this week?
Monday’s 20.3% gain came on a day when the whole AI hardware group rose. Ten AI hardware stocks TECHi tracks gained 13.6% on average that day, when Nvidia’s board reinstated Jensen Huang, as TECHi reported, and CoreWeave, the tenant at Applied Digital’s largest campus, rose 22.3%. On Tuesday Applied Digital fell 11.6% and CoreWeave 11.8%, and on Wednesday Applied Digital edged up 0.6%.
CoreWeave was up 5.7% at $45.00 before Friday’s open. Through Wednesday, Applied Digital had lost 31.0% in November and CoreWeave 22.4%, against a 17.9% fall in the Philadelphia Semiconductor Index, which at Wednesday’s close was its second-worst November since 1999, as TECHi reported on Thursday.
At Wednesday’s close, Applied Digital’s market value was about $3.7 billion, and about $4.0 billion at Friday’s pre-market price. That is small next to the $41.13 billion of contracted base-term rent, but the two numbers are not directly comparable: the rent arrives over 15 to 18 years, most of the buildings still have to be paid for, and lenders and preferred investors are paid before common shareholders.
What conditions still apply?
Several parts of the plan are not yet settled. Besides the power approvals for the new lease, a 100-megawatt expansion at Polaris Forge 2 is in negotiation and not signed, and the company’s goal of 3.5 to 4 gigawatts of capacity by 2030 is not contracted, according to the presentation.
Applied Digital also signed a power purchase agreement on October 4 with Base Electron, an independent power producer it helped launch to build generation in its North Dakota region. Base Electron is partly owned and managed by some Applied Digital officers and directors in their own capacity, along with third parties, and Wes Cummins is chief executive of both companies; Applied Digital’s board approved the agreement on the recommendation of a related-party committee, and Applied Digital shareholders own about 10% of Base Electron. Base Electron can end the agreement if financing for its plant has not closed by March 31, 2027, and the plant has not been built, the presentation says.
What to watch
- Where the new 150-megawatt campus is, and whether its power supply agreement is approved.
- Project financing for Delta Forge 1 and Polaris Forge 3, which the company expects in the first quarter of 2027, and for Delta Forge 2 in the second quarter.
- Draws on the bridge loan and the B. Riley preferred facility, and the share count in Applied Digital’s next quarterly report.
- Whether the 100-megawatt Polaris Forge 2 expansion is signed.
- Base Electron’s financing deadline of March 31, 2027.
- Friday’s shortened session, which ends at 1 p.m. Eastern and settles November for the stock.